We recently completed 'phase one' of our LED
lighting programme. This involved upgrading communal lighting in
corridor stairs and exterior of buildings in blocks on Council
Housing Estates.
We are now seeking approval to compliantly direct award the 'phase
2' contract (estimated at £850,000) to Openview Security
Solution Limited via the London Housing Consortium Framework, LOT
'Whole House Refurbishments and Associated Works framework
(WH2)'.
Decision type: Key
Reason Key: Expenditure/Income above £300K - Revenue up to £500k and Capital up to 1.5m;
Decision status: Recommendations Approved
Wards affected: (All Wards);
Notice of proposed decision first published: 16/08/2023
Report access: Open;
Report Type: Key Decision;
Decision due: October 2023 by Strategic Director of the Economy Department
Lead member: Cabinet Member for Housing and Homelessness
Department: The Economy department
Contact: Richard Buckley Email: richard.buckley@lbhf.gov.uk.