We have recently completed phase 1 and phase 2
of the LED lighting programme for block communal lighting. To keep
on track with our LED lighting programme time and specification
delivery targets, we now need to embark on phase 3 of the LED
programme in Q4 of 2024.
This will involve LED lighting upgrades to the following
properties: 22 Housing Blocks, 28 Tenants Resident Association
Halls and 83 plant rooms which Contains Boilers, Pumps etc. We
estimate that the cost of this work will be around
£1,200,000.
We recommend the approval of a compliant contract direct award to
Openview Security Solutions Limited via the London Housing
Consortium Whole House Refurbishments and Associated Works
framework Framework. The contract will be for
£1,200,000.
Decision type: Key
Reason Key: Expenditure/Income above £300K - Revenue up to £500k and Capital up to 1.5m;
Decision status: For Determination
Wards affected: (All Wards);
Notice of proposed decision first published: 01/11/2024
Report Type: Key Decision;
Decision due: 5 Dec 2024 by Executive Director of Finance and Corporate Services
Lead member: Cabinet Member for Housing and Homelessness
Lead director: Executive Director of Finance and Corporate Services
Department: The Economy department
Contact: Nick Marco-Wadey Email: Nick.Marco-Wadey@lbhf.gov.uk Tel: 07988490264.