Issue details

Phase 3 LED lighting contract for block communal lighting.

We have recently completed phase 1 and phase 2 of the LED lighting programme for block communal lighting. To keep on track with our LED lighting programme time and specification delivery targets, we now need to embark on phase 3 of the LED programme in Q4 of 2024.

This will involve LED lighting upgrades to the following properties: 22 Housing Blocks, 28 Tenants Resident Association Halls and 83 plant rooms which Contains Boilers, Pumps etc. We estimate that the cost of this work will be around £1,200,000.

We recommend the approval of a compliant contract direct award to Openview Security Solutions Limited via the London Housing Consortium Whole House Refurbishments and Associated Works framework Framework. The contract will be for £1,200,000.

Decision type: Key

Reason Key: Expenditure/Income above £300K - Revenue up to £500k and Capital up to 1.5m;

Decision status: For Determination

Wards affected: (All Wards);

Notice of proposed decision first published: 01/11/2024

Report Type: Key Decision;

Decision due: 5 Dec 2024 by Executive Director of Finance and Corporate Services

Lead member: Cabinet Member for Housing and Homelessness

Lead director: Executive Director of Finance and Corporate Services

Department: The Economy department

Contact: Nick Marco-Wadey Email: Nick.Marco-Wadey@lbhf.gov.uk Tel: 07988490264.