Issue details

Procurement Strategy – Electrical Lateral Mains Upgrade Works (Approximately 81 Blocks)

Procurement Strategy to procure a contractor to carry out upgrade/replacement works in relation to Electrical Lateral Mains (ELMs) across 81 blocks. ELMs provide the electrical distribution system in multi-occupancy buildings (landlord electrical distribution infrastructure) and the ‘Housing Revenue Account (HRA) 12 year Asset Management Capital Strategy’ (approved by Cabinet on 6th September 2021) listed replacement works in relation to Lateral Mains to be undertaken. Carrying out these works complies with the approved capital strategy.

Decision type: Key

Reason Key: Expenditure/Income over £5m & policies or new income, reserves use, overspend over £300K;

Decision status: No longer a Key Decision

Wards affected: (All Wards);

Notice of proposed decision first published: 14/04/2022

Report access: Open;

Report Type: Key Decision;

Decision due: 5 Dec 2022 by Cabinet

Lead member: Cabinet Member for Housing and Homelessness

Lead director: Strategic Director of the Economy Department

Department: The Economy department

Contact: Dominic D Souza, Commercial Manager Email: Dominic.DSouza@lbhf.gov.uk.

What is the total value of the decision?: Yes

 

Translate this website