Issue details

Authority to Enter into a Pre-Construction Services Agreement (PCSA) with a Contractor to Progress the Town Hall Refurbishment and Fit-Out Contract

This report recommends that a Pre-Construction Services Agreement (PCSA) is entered into for the completion of the technical design (RIBA Stage 4) for the refurbishment and fit-out of the Town Hall. The budget has already been approved by Cabinet and Full Council. This recommendation on the report is to confirm appointment of the Contractor which will need drawdown on the approved budget of £2.8m.


Decision type: Key

Reason Key: Expenditure/Income - Revenue between £500,000 and £5m and Capital between £1.5m and £5m;

Decision status: Recommendations Approved

Wards affected: Hammersmith Broadway;

Notice of proposed decision first published: 05/03/2020

Report access: Open;

Report Type: Key Decision;

Decision due: 14 May 2020 by Cabinet Member for the Economy

Lead director: Strategic Director of the Economy Department

Department: The Economy department

Contact: David Burns, Head of Housing Strategy Email: David.Burns@lbhf.gov.uk, Sazeda Ibrahim Email: Sazeda.Ibrahim@lbhf.gov.uk Tel: 07710 021579.

Reason No Public Access:

Decisions