Hammersmith Bridge - Essential Work Leading to Strengthening and Restoration Project

11/10/2022 - Hammersmith Bridge – Essential Work Leading to Strengthening and Restoration Project

1.         To approve a new capital budget of up to £5m in 2022/23, to be funded from borrowing (increase to the Capital Financing Requirement), pending confirmation of two thirds funding contributions from the Department for Transport (DfT) and Transport for London (TfL).

 

2.         To approve this budget to fund:

 

I.            a diversion of a Cadent gas mains off and away from the bridge.

 

II.         the progression and obtainment of a planning application for a potential temporary truss.

 

III.     the further progression of contract/procurement development for options for the full refurbishment of Hammersmith Bridge.