Procurement Strategy for construction of a new community centre at Linacre Court W6

01/07/2022 - Procurement Strategy for construction of a new community centre at Linacre Court W6

1.    That the Strategic Director of Economy, in consultation with the Cabinet Member for Housing, approves the procurement strategy proposing a limited competitive tendering procedure to source a supplier for the construction of a new community hall at Linacre Court W6. The project budget is £327,000 and estimated contract period will be 40 weeks.

 

2.    That the Strategic Director of Economy  approves a virement of £31,000 from the uncommitted Compliance Concrete/Structural works Contingency so that the procurement costs of £327,000 can be fully funded from the relevant project budget within the HRA Asset Management Compliance Strategy and Capital Programme.