1. That the Cabinet Member for Housing approves a budget virement of £142,000 to the Linacre Court scheme from the compliance concrete/structural works contingency budget.
2. That the Strategic Director for the Economy, in consultation with the Cabinet Member for Housing, approves the procurement strategy proposing a competitive tendering procedure to source a supplier for the construction of a new community hall at Linacre Court W6. The project budget is £327,000 and the estimated contract period will be 40 weeks.