Procurement Strategy and Direct Award of contract to provide consultancy support for various schemes within the Housing Capital Programme

03/10/2021 - Procurement Strategy and Direct Award of contract to provide consultancy support for various schemes within the Housing Capital Programme

1.    That Appendix 1 of this report is currently exempt from disclosure on the grounds that it contains information relating to the financial or business affairs of a particular person (including the authority holding that information) under paragraph 3 of Schedule 12A of the Local Government Act 1972, and in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information.

 

2.    That the Cabinet Member for Housing approves the procurement strategy proposing the use of the South East Consortium Consultancy Framework direct award procedure for the provision of multi-disciplinary services to enable the delivery of projects outlined in Appendix 1.

 

3.    That the Cabinet Member for Housing approves the award of a contract to Baily Garner under the South East Consortium Consultancy Framework direct award procedure for the provision of multi-disciplinary services to enable the delivery of the Phase 1 projects outlined in Appendix 1 at an estimated total value of £2.1m. The contract is expected to start in October 2021 for an estimated period of up to four years.

 

4.    To note that the Phase 1 commissions will be for urgent safety works at Edward Woods and Charecroft estates; the continuation of complex void works and spandrel panel removal; the grant-funded retrofit of West Kensington estate houses; and window replacement and associated works to West Kensington towers. Each workstream will be subject to the agreement of specific scope of services and there will be negotiations on fee proposals taking into account the overall volume of work being awarded. Value for money, capacity, and delivery of social value will be key assessments for each commission.

 

5.    To note that the commission for the Phase 2 projects will be subject to further market testing, anticipated to be via a mini-competition under the SEC or other framework.

 

6.    To note that the estimated fees detailed in Appendix 1 will be recalculated based on the total contract value and service proposal for each project and will be detailed in individual works contract award reports.