CAPITAL PROGRAMME MONITOR & BUDGET VARIATIONS, 2020/21 (THIRD QUARTER)

02/02/2021 - Capital Programme Monitor & Budget Variations, 2020/21 (Third Quarter)

1.    To approve the proposed budget variations to the capital programme totalling £1.6m (summarised in Table 1 and detailed in Appendix 2).

 

2.    To approve additional budget of £1,223,000 funded from borrowing (£432,000) and external grants (£791,000), to complete various transport and parks schemes (see Appendix 2 for detail).

 

3.    To approve an additional budget of £0.9m, and funding acceptance regarding a grant award from BEIS (Department for Business, Energy and Industrial Strategy) for Social Housing Decarbonisation and note that this will be supported by £1.6m of funding from the existing HRA Asset Management and Compliance Programme.

 

4.    To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 26, 27 and 28.