1. To approve the proposed budget variations to the capital programme totalling £1.6m (summarised in Table 1 and detailed in Appendix 2).
2. To approve additional budget of £1,223,000 funded from borrowing (£432,000) and external grants (£791,000), to complete various transport and parks schemes (see Appendix 2 for detail).
3. To approve an additional budget of £0.9m, and funding acceptance regarding a grant award from BEIS (Department for Business, Energy and Industrial Strategy) for Social Housing Decarbonisation and note that this will be supported by £1.6m of funding from the existing HRA Asset Management and Compliance Programme.
4. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 26, 27 and 28.