It is recommended that the Leader of the Council:

1.1.            Approves an update to the Business Case and Procurement Strategy for the Housing Capital Programme to 31st March 2020 as agreed in September 2018 in respect of programmed fire safety works, by agreeing an allocation of the fire safety works to the Council’s in-house repairs team rather than seek external contractors.

1.2.            Approves the transfer of £6m of the capital budget for the works set out in Appendix 1 (being £20m for the period from 17th April 2019 to 31st March 2020) to the Council’s in-house repairs service, H&F Maintenance.