Barclay Close Lifts A–D, Ethel Rankin Crt & The Grange (Lisgar W14) Lifts A & B - Modernisation of the Passenger Lifts
- That funding for this
scheme is contained within the 2012/13 Housing Capital Programme
which was approved by Cabinet on 11 December 2011 and by Budget
Council on 29h February 2012 (within this
£80k was included in 2012/13 and £690k in 2013/14, now
revised to £770k - excluding professional fees - in 2012/13
in order to accelerate delivery of the project funded by savings
and movement on other programmes), be noted.
- That the contract is expected to be
awarded on 18February 2013, and has a contract period of 45 weeks
from the date of the award, with start on site expected on 20 May
2013, be noted.