No. | Item |
---|---|
To Appoint A Contractor To Deliver Shared Services Domestic Violence Perpetrator Pilot PDF 188 KB Additional documents: Decision: Decision taken by the Cabinet Member on: 24 September 2015
1. To approve a waiver to H&F Contract Standing Orders (under CSO 3) for the requirement to complete a competitive tendering exercise (advertise the opportunity and seek 3 quotations) according to the requirement under CSO’s 11.2, and allow the award of a contract to deliver a pilot scheme to increase the identification of and interventions with perpetrators of domestic abuse for reasons set out in section 3 of this report.
2. That the Cabinet Member approves the appointment of Domestic Violence Intervention Project (DVIP) a registered charity (No. 1083549) to deliver the pilot scheme which will run from 1st October 2015 to 30th September 2016 at a total cost £50,000 to the Council, with the funding being provided by MOPAC.
3. That the Cabinet Member agrees to delegate the decision to extend the pilot scheme up to a period of 12 months to the Director of Safer Neighbourhoods. This is conditional upon costs not exceeding a further £50,000 (should such funding become available to the Council after September 2016) and that the scheme has delivered the outcomes detailed at section 5 of this report.
|
|
Additional Resources For Business Intelligence - Council Tax PDF 99 KB Decision: Decision taken by the Cabinet Member on: 21 September 2015
To recruit two officers to undertake the additional work, outlined in section 1.3 above, for an initial pilot period of 6 months at a cost of £45k with funding from the Efficiency Projects Reserve.
|
|
Legal Charges For Section 106 Agreements - Increase To Hourly Rate Charge PDF 163 KB Decision: Decision taken by the Cabinet Member on: 6 October 2015
That the hourly rate, to cover the Council’s in house legal fees in connection with section 106 agreements and undertakings, be increased to £220 an hour.
|
|
ICT Transition Programme Additional Funding PDF 116 KB Decision: Decision taken by the Cabinet Member on: 28 September 2015
To approve £94,261 one-off towards the additional costs of this ICT transition programme. The source for this is the IT Enablers fund.
|
|
Improvements To Play Landscaping At Hammersmith Park PDF 145 KB Additional documents: Decision: Decision taken by the Cabinet Member on: 29 September 2015
To approve a waiver under Contract Standing Order 11 for the requirement to (a) advertise the opportunity and (b) seek public quotations using the e-tendering system and the Government‘s Contracts Finder portal for the reasons set out in section 3 on the report.
To approve the award of a contract for works to Playcubed Ltd. to carry out the relevant playground improvement works to the value of £39,090.
|
|
Projects For Annual Parks Capital Programme 2015/16 PDF 128 KB Decision: Decision taken by the Cabinet Member on: 29 September 2015
To approve the full list of new parks projects (option 3 on the report). |
|
Nomination Of La Governor - Hammersmith Academy PDF 157 KB Decision: Decision taken by the Cabinet Member on: 9 October 2015
That the following LA Governor nomination be made:
That Ms Grace Oliver is nominated for re-appointment as LA Governor for Hammersmith Academy for a four year term. |
|
Nomination Of LA Governor - Sulivan Primary School PDF 156 KB Decision: Decision taken by the Cabinet Member on: 16 October 2015
That the following LA Governor nomination be made:
That Ms Caroline Langton is nominated for appointment as LA Governor for Sulivan Primary School for a four year term of office. |
|
Appointment of LA Governor - Avonmore Primary PDF 156 KB Decision: Decision taken by the Cabinet Member on: 16 October 2015
That the following LA Governor nomination be made:
That Cllr Joe Carlebach is nominated for re-appointment as LA Governor for Avonmore Primary School for a four year term of office.
|
|
Earls Court - Appointment Of Tcc To Undertake Resident Engagement PDF 190 KB Decision: Decision taken by the Cabinet Member on: 16 October 2015
1. To seek approval to waive the requirements of Contract Standing Orders and to make a direct award to The Campaign Company Limited (TCC) at a fee of up to £33,000, to deliver resident egagement activities
2. To delegate to the Director of Planning and Growth authority to make any necessary ancillary decisions. |
|
Business Case For The Retendering Of The Term Contract For Tree Maintenance PDF 177 KB Decision: Decision taken by the Cabinet Members on: 16 November 2015
1. Approve the Business Case for re-tendering of the Tree Maintenance Contract as set out in the report.
2. To note that the final contract award will be subject to cabinet approval as a key decision.
3. To agree an extension to the existing contract by up to three months to provide a transitional period for the tendering process to be completed.
|
|
Vereker Road No 1, Vereker Road No 25, Vereker Road No 50, London W14 And Nos 5 - 48 Walham Green Court, Fulham Road, London, SW6 2DH: The Modernisation Of 5 Existing Passenger Lifts
Decision: Decision taken by the Cabinet Member on: 2 October 2015
That the recommendations contained in the exempt report be approved. |
|
Re-Provision Of Daytime And Out Of Hours Contact Centre Services
Decision: Decision made by the Cabinet Member on: 4 November 2015
That the recommendations contained in the exempt report be approved.
|
|
Continuation Of School Meals Contract With Eden Foodservice Ltd.
Decision: Decision taken by the Cabinet Member on: 9 October 2015
That the recommendation contained in the exempt report be approved.
|
|
Appointments To A Multi-Supplier Framework For Semi-Independent Living Service And Agreement To Enter Into Call-Off Contracts
Decision: Decision taken by the Leader on 15 October 2015 and the Cabinet Member for Children and Education on 4 September 2015
That the recommendations contained in the exempt report be approved.
|
|
Permission To Award A 6 Month Contract To Liberty Printers For Printing Of Statutory Documents, And A 6 Month Contract With Rr Donnelley For Scanning Of Incoming Mail And Payment Processing
Decision: Decision taken by the Cabinet Member on: 19 October 2015
That the recommendations contained in the exempt report be approved.
|
|
Direct Award For Supported Employment Whilst Wider Procurement Is Concluded
Decision: Decision taken by the Cabinet Member on: 18 June 2015
That the recommendations contained in the exempt report be approved.
|
|
Approval To Accept The Terms Of Counter Offers Made By The Two Remaining Leaseholders Of 18 And 27 Edith Summerskill House
Decision: Decision taken by the Cabinet Member on: 3 November 2015
That the recommendations contained in the exempt report be approved.
|