Minutes:
Councillor Lisa Homan presented the report on behalf of Councillor Andrew Jones. She stated that the project at Sulivan Court was one which the Council had committed todeliver as part of the Asset Management Compliance Strategy and CapitalProgramme approved by Cabinet in July 2019. The proposed projects atBecklow Gardens and Emlyn Gardens were similarly guided by theprinciples of the strategy to improve the Council’s estates.
RESOLVED:
It is recommended that Cabinet approves the Business Case & Procurement Strategy for procurement of each of the following works contracts:
1. The major refurbishment of Sulivan Court estate SW6 at an estimated value of £6.081m.
2. The major refurbishment of Emlyn Gardens estate W12 at an estimated value of £4.5m
3. The major refurbishment of Becklow Gardens estate W12 at an estimated value of £4.3m
4. Approves a £5.8m capital budget, funded by HRA borrowing, to progress Becklow Gardens and Emlyn Gardens with the remaining £3m funded from uncommitted and unallocated budgets identified within the overall programme.