102 Capital Programme Monitor & Budget Variations, 2018/19 (Second Quarter) PDF 311 KB
Minutes:
1. To approve the proposed budget variations to the capital programme totalling £15m (summarised in Table 1 and detailed in Appendix 2).
2. To approve use of £42k of Short Breaks capital grant to reduce the funding shortfall for the Queen’s Manor project.
3. To approve capitalisation of ICT desktop strategy costs of £3.7m of which £3.3m is to be funded from GF mainstream resources and £0.4m from HRA contributions.
4. To approve write-off of capitalised expenditure to date of £0.383m for Becklow Gardens and £0.547m for Jepson House as these schemes will now be delivered through the Affordable Housing Delivery Framework rather than directly by the Council. The write-off will be funded from HRA earmarked reserves.