Issue - meetings

Linford Christie Stadium

Meeting: 13/05/2013 - Cabinet (Item 215)

215 Linford Christie Stadium : General internal and external refurbishment of changing room public facilities and major upgrade of commercial kitchen pdf icon PDF 66 KB

Additional documents:

Minutes:

That an order be placed under the Measured Term Contract for Non-Housing Projects 2011/2015 with Mulalley & Company Limited, based on a framework agreement with three contractors, at an estimated works cost of be £264,450 which includes a contingency sum of £22,470 to which fees of £ £39,667 will be added, making a total cost of £304,117, be approved.