Issue - meetings

Hammersmith Library Refurbishment

Meeting: 23/04/2012 - Cabinet (Item 235)

235 Hammersmith Library refurbishment pdf icon PDF 74 KB

Additional documents:

Minutes:

1.      That the sum of £200,000 received from the Section106 fund as set out in this report be used to enable consultation with customers and stakeholders to commence, to scope and determine the costs of the building works and to engage an architect for the design element of the project.

 

2.      That the sum of £725,000 released from the Section 106 fund on the commencement of the construction of the South Building of Hammersmith Car Park be used to commence the build and refit of the library.

 

3.      That £725,000 be released from the commencement of the construction of the North Building (timeframe to be advised by developers).