Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Proposing improvements to the existing 15 tennis courts, to include re-introduction of floodlights to illuminate 5 courts, resurfacing of all courts, reconfiguring court layout to include junior courts and 12 LTA courts as well as boundary fencing. Approval is sought to delegate authority to appoint the contractor and for total expenditure of £340k, comprising LBHF capital funding of £170k; £150k of match grant funding from LTA; and £20k from Queens Club.
Agreed:
1. That the budget expenditure for delivery of the tennis improvement scheme at Bishops Park of £340,000 be approved.
2. That authority be delegated to officers (Director of Residents Services) to award contract(s) to deliver the project.
Report author: Paul Bassi
Publication date: 31/03/2010
Date of decision: 29/03/2010
Decided at meeting: 29/03/2010 - Cabinet
Effective from: 08/04/2010