Decision Maker: Executive Director of Finance and Corporate Services
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
The report proposes the direct award of a
contract for the completion of major works to Linacre Court
W6
Decision:
- To agree that Appendix 1 is not for
publication on the basis that it contains information relating to
the financial or business affairs of any particular person
(including the authority holding that information) as set out in
paragraph 3 of Schedule 12A of the Local Government Act 1972 (as
amended).
- That the Executive Director for
Finance and Corporate Services, in consultation with the Cabinet
Member for Housing and Homelessness, approves the award of a
contract to Greyline Group Ltd. in the sum of £438,013.09.
The works have a 20 week programme and are expected to start during
August 2025 and complete during December 2025.
- That the Executive Director for
Finance and Corporate Services, in consultation with the Cabinet
Member for Housing and Homelessness, approves the contingency sum
detailed in exempt Appendix 1 to deal with any unforeseen matters
that may arise.
Reasons for the decision:
1.
This award report is submitted for approval by the Cabinet Member,
in accordance with paragraph 18 of the CSOs.
2.
A decision is required to progress the appointment of a contractor
to complete the outstanding works and bring an important asset into
use.
Alternative options considered:
- In October 2023 the Cabinet Member
for Housing and Homelessness approved the appointment of Breyer
Group plc (Breyer) via Lot 1b (Major Refurbishment over £1m)
of the South East Consortium Internal and External Works Framework
(the “Framework”), to undertake major refurbishment
works to 1-69 Linacre Court W6. The works comprise major
refurbishment of the residential tower block and the construction
of a new community centre on adjacent land. The contract started in
January 2024.
- On 1 April 2025 Breyer filed a
notice of appointment of an administrator due to financial
difficulties. Breyer therefore ceased trading as of this date and
works on Linacre Court stopped.
- The works to the tower block are
substantially complete with isolated snagging and minor
redecorations outstanding. The community hall building has been
constructed with minor items of work pending to the roof and
windows.
- However, the internal works have
been limited with progress needed for mechanical and electrical
services, heating system, kitchen facilities, WC, and finishes to
walls and floors. External landscaping works to bring the new
community centre into use are scheduled for the end of the
programme.
- It is in the interests of the
Council and residents to appoint a contractor to complete the works
as quickly as possible and officers have taken steps to progress
this in a compliant manner.
- A waiver of the CSOs necessitating a
competitive process has been approved on the grounds that the
contract is for works that are required in circumstances of extreme
urgency that could not reasonably have been foreseen.
- Greyline Group Ltd. is currently
working on void properties in the borough and have previously
successfully delivered various insurance-related projects to a high
standard. Greyline Group Ltd. met with officers at Linacre Court on
30 April 2025 to review the site and better understand the
Council’s requirements, not only in relation to the
outstanding works but also assuming responsibility for the defects
liability period on works already completed.
Publication date: 21/07/2025
Date of decision: 21/07/2025
Effective from: 25/07/2025