Decision details

Procurement Strategy for the demolition of Linford Christie Changing room and shower block and replacement

Decision Maker: Executive Director of Place

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Demolition of Linford Christie Changing room and shower block and the provision of design, purchase and installation of six purpose-built WC, changing room and shower facility porta cabins for Linford Christie

Decision:

1.            To approve the procurement strategy, which will result in conducting an open tender competition for the demolition of the main building with a contract estimated value of £600,000.

 

2.            To approve the procurement strategy, which will result in conducting an open tender competition for the purchase of 9 purpose-built portacabins incorporating WC, changing room and shower facilities for Linford Christie with a contract estimated value of £650,000.

 

Reasons for the decision:

To bring the main building into a suitable state for re-occupation would require a very large investment, estimated around £6.5m. This procurement of demolition and purchase and install nine on site portacabins would be a good medium-term solution to retain the services at Linford Christie until the council had the time to evaluate fully its decision on the future of the stadium and any future investments at an estimated costs of £1.25m and be good for at least 8-10 years.

 

Alternative options considered:

Option 1: To Do Nothing.

Option 2: Propping Wall and Hiring portacabins.

Option 3 – Demolition and Replacement: This option is recommended.

 

Publication date: 14/06/2024

Date of decision: 11/06/2024

Effective from: 20/06/2024