Civic Campus Enhanced Investment

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Update on progress with the Civic Campus and recommendation for financial investment

Decision:

 

1.  Cabinet notes that Appendices 1, 3 and 4 are not for publication on the basis that they are legally privileged as set out in paragraph 5 of Schedule 12A of the Local Government Act 1972.

 

2.  Cabinet approves estimated additional capital funding of £21.4m (£19.2m plus £2.2m contingency) necessary to complete the construction and fit out of the new Town Hall building, associated fees and other works (including necessary changes to the specification of works).

 

3.  Cabinet notes estimated additional one-off revenue costs of £1.6m (£1.4m plus £0.2m contingency) necessary for project costs related to returning to the Town Hall and additional dilapidations provision.

 

4.  Cabinet approves the entering into by the Council of a deed of variation of the Construction Contract dated 1st December 2020 necessary to implement the proposed addition investment and changes to the specification of works the details of which are included at Appendix 1

 

5.  Cabinet approves the procurement strategy for design and assurance services to enable the award of a contract for 11 months for an estimated value of £ 860,000 commencing March 2023. 

 

6.  Cabinet approves the award of a contract to Entec Si for Audio Visual services via G-Cloud 13 for a value of £328,060 with a contract term of 1 year commencing from 1st February 2023.

 

7.  Cabinet approves the increase of the long-term leasehold interest to the LLP from a term of 255 years to a term of 999 years, in line with GLA guidance outlined in Appendix 1, but otherwise on the same terms as previously agreed.

 

8.  Cabinet approves the variation to the Conditional Agreement for Lease(CAL) to include a mechanism for payment by the LLP of any additional consideration that may be due in respect of the leases to be granted to the LLP following the grant of those leases in advance of practical completion of the glass pod works should the construction costs for the glass pod works be less than the acceptable land value, in line with the advice to be provided relating to potential tax implications.

 

9.  Cabinet approves a delegation to the Director of Finance, in consultation with the Cabinet Member for Finance and Reform, authority to temporarily increase the Capital Finance Requirement (CFR), for technical accounting purposes, to fund any capital debtor which may arise in the event of timing differences between the drawdown of each lease and the recognition of consideration by the Council, (up to a maximum of £11.9m reflecting the total value of leases proposed to be granted ahead of practical completion of the Pod works).

 

10.         Cabinet approves a delegation to the Strategic Director of the Economy in consultation with the Assistant Director, Legal Services authority to take all necessary steps to facilitate the decisions in 1-7. 

 

Report author: Jonathan Skaife

Publication date: 07/02/2023

Date of decision: 06/02/2023

Decided at meeting: 06/02/2023 - Cabinet

Effective from: 11/02/2023