Decision Maker: Cabinet Member for Housing and Homelessness
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Report seeks approval of the Business Case
& Procurement Strategy for the major refurbishment of Maystar
EstateW14. This project is one which the Council has committed to
deliver as part of the Asset Management Compliance Strategy and
Capital Programme approved at 1st July Cabinet 2019.
That the Cabinet Member for Housing approves the Procurement Strategy, attached at Appendix 1, to use the South East Consortium for the major refurbishment of Maystar Estate W14 at an estimated value of £4.750m for a proposed contract period of 52 weeks.
The decision is required to initiate the tender process to appoint a contractor to carry out the works required in these buildings.
As described in the report.
Publication date: 20/08/2020
Date of decision: 19/08/2020
Effective from: 25/08/2020