HRA Housing Capital Programme 2017/18-2020/21

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

This report provides specific details of the proposed 2017/18 housing capital programme and proposes budget envelopes for the following two years

Decision:

1.            To approve the projects and schemes identified in this report (see Appendix 1) which will form the 2017/18 and 2018/19 HRA Housing Capital Programme to the value of £33.523m for 2017/18 and £29.634m for 2018/19 (budget envelopes approved at Full Council on 22nd February 2017 as part of the Council’s four-year capital programme). To note the risks attached to the 2018/19 budget envelope.

 

2.            To approve the budget envelope of £28.826 million for 2019/20 and £32.475 million for 2020/21 and note the funding streams identified as part of the HRA Housing Capital Programme. This recommendation is subject to future quarterly / annual changes to the overall Council capital programme as set out in future reports to Cabinet.

 

3.            To delegate authority to the Director of Housing Services, in consultation with the Cabinet Member for Housing, to issue orders for work and projects to be carried out using, where appropriate, the council’s ten-year Term Partnering Contract with Mitie Property Services, approved by Cabinet 8th April 2013 or any other suitable contracts which are put in place in the period in accordance with Contract Standing Orders para 17.

 

4.            To delegate authority to the Director of Housing Services, in consultation with the Cabinet Member for Housing, to approve future amendments to the programme for operational reasons where such amendments can be contained within the overall approved budget envelope and available resources.

 

Report author: Vince Conway

Publication date: 29/03/2017

Date of decision: 27/03/2017

Decided at meeting: 27/03/2017 - Cabinet

Effective from: 10/04/2017