Decision details

ICT transition funding and viability : Exempt (E)

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

H&F Bridge Partnership (HFBP) currently provides all ICT services to H&F. The HFBP service contract expires on 31 October 2016, at which time all HFBP services must have moved to other suppliers or across to the Shared Services ICT function. The first phase of this transition to do programme definition and process analysis work is underway. Meantime the second phase needs to start. This proposes the call-off from three London-wide Framework contracts (distributed computing, servicedesk and data centres) let in 2012 by the Shared Service ICT.

Decisions:

That the recommendations in the exempt report, be noted.

 

Report author: Jackie Hudson

Publication date: 09/07/2015

Date of decision: 06/07/2015

Decided at meeting: 06/07/2015 - Cabinet

Effective from: 13/07/2015

  • Restricted enclosure  View reasons restricted
  •