Decision Maker: Cabinet Members' Decisions
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
Decision taken by the Cabinet Member on: 28 June 2014
1. That approval be given for the works to be procured via Amey Community Limited (ACL) in accordance with the approved Terms and Conditions of the Tri-Borough TFM contract.
2. That approval be given to award the contract to ACL and their sub-contractor (Core Projects Limited) for works to create a new meeting room in the sum of £39,763.79, plus a 10% Contingency Sum of £3,976.00 and associated fees of £2,863.00, making a total cost for approval of £46,602.79.
Publication date: 03/07/2014
Date of decision: 09/07/2014
Decided at meeting: 09/07/2014 - Cabinet Members' Decisions