Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
The report seeks approval to let a contract to
modernise the existing passenger lifts at Barclay Close Est, Ethel
Rankin Court and the Grange (Lisgar terrace)
Decision:
- That funding for this
scheme is contained within the 2012/13 Housing Capital Programme
which was approved by Cabinet on 11 December 2011 and by Budget
Council on 29h February 2012 (within this
£80k was included in 2012/13 and £690k in 2013/14, now
revised to £770k - excluding professional fees - in 2012/13
in order to accelerate delivery of the project funded by savings
and movement on other programmes), be noted.
- That the contract is expected to be
awarded on 18February 2013, and has a contract period of 45 weeks
from the date of the award, with start on site expected on 20 May
2013, be noted.