The report seeks approval to let a contract to modernise the existing passenger lifts at Barclay Close Est, Ethel Rankin Court and the Grange (Lisgar terrace)

Decision:

  1. That funding for this scheme is contained within the 2012/13 Housing Capital Programme which was approved by Cabinet on 11 December 2011 and by Budget Council on 29h February 2012 (within this £80k was included in 2012/13 and £690k in 2013/14, now revised to £770k - excluding professional fees - in 2012/13 in order to accelerate delivery of the project funded by savings and movement on other programmes), be noted.

 

  1. That the contract is expected to be awarded on 18February 2013, and has a contract period of 45 weeks from the date of the award, with start on site expected on 20 May 2013, be noted.

 

Report author: Velma Chapman

Publication date: 12/02/2013

Date of decision: 11/02/2013

Decided at meeting: 11/02/2013 - Cabinet

Effective from: 18/02/2013