Decision details

Phase 3 LED Lighting Contract for Block Communal Lighting

Decision Maker: Executive Director of Finance and Corporate Services

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

We have recently completed phase 1 and phase 2 of the LED lighting programme for block communal lighting. To keep on track with our LED lighting programme time and specification delivery targets, we now need to embark on phase 3 of the LED programme in Q4 of 2024.

This will involve LED lighting upgrades to the following properties: 22 Housing Blocks, 28 Tenants Resident Association Halls and 83 plant rooms which Contains Boilers, Pumps etc. We estimate that the cost of this work will be around £1,200,000.

We recommend the approval of a compliant contract direct award to Openview Security Solutions Limited via the Fusion 21 ‘Building Safety and Compliance’  Framework. The contract will be for £1,200,000.’

Decision:

To approve the procurement strategy and contract award approval of a compliant contract by the direct award procedure to OpenView Security Solutions Limited via the Fusion 21 ‘Building Safety and Compliance’ Framework. This is a blended call-off covering the ‘lighting equipment and emergency lighting’ and ‘Warden call and Tele-Health' categories’. The contract will be for £1,200,000.

 

Reasons for the decision:

In Quarter 4, 2024, the service needs to begin ‘phase 3’ of the programme for LED lighting upgrades to communal lighting in corridor stairs and exterior of buildings, plant rooms and blocks on Council Housing Estates. The award of this contract is critical in delivering these works.

 

Alternative options considered:

·         Option 1: Deliver the supplies, services, and/or works in-house (make/buy decision) – Not Recommended

 

·         Option 2: Undertake a full regulated procurement process, advertised to the market – Not Recommended

 

·         Option 3: Procure using a compliant framework or Dynamic Purchasing System (DPS) by way of mini competition – Not Recommended

 

·         Option 4: Procure using a compliant framework or Dynamic Purchasing System (DPS) by way of a Direct Award – Recommended

 

Publication date: 24/01/2025

Date of decision: 14/01/2025

Effective from: 30/01/2025

Accompanying Documents: