Decision details

Contract Award Report for Cycle Hangar Roll Out 2024-27

Decision Maker: Cabinet Member for Public Realm

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To enable the roll out of up to 500 Cycle Hangars across the borough, thereby meeting our current residents' waiting list which is 3000-strong

Decision:

Reasons for the decision:

There is considerable demand from H&F residents for secure, dry, clean roadside cycle storage and this procurement will meet current demand.  Further, H&F declared a climate emergency in July 2019 and is committed to reaching net zero carbon by 2030.  

 

Alternative options considered:

Waltham Forest Framework was used to procure Cyclehoop Ltd and ran a mini competition between the only two suppliers on the framework.

 

Waltham Forest Framework was used because it was a compliant route that had been used by a number of boroughs across London to successfully roll out large numbers of cycle hangar provision, and to meet significant resident demand in a timely fashion.  The key benefit to using the Framework was ease of procurement through an existing, trusted channel.

 

Publication date: 21/12/2023

Date of decision: 19/12/2023

Effective from: 29/12/2023

Accompanying Documents: