Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
This report provides a financial update on the
council’s capital programme and requests approval for budget
variations to the capital programme.
1. To note the net forecast decrease in 2021/22 capital expenditure of £12m (9.4% of the approved budget). The variations are detailed in Appendix 2.
2. To approve the updated four-year capital programme 2021-2025 of £473.2m as detailed in Appendix 1.
3. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 20-22.
Report author: Andrew Lord
Publication date: 08/02/2022
Date of decision: 07/02/2022
Decided at meeting: 07/02/2022 - Cabinet
Effective from: 11/02/2022
Accompanying Documents: