This report provides a financial update on the
council’s capital programme and requests approval for budget
variations to the capital programme.
1. To note the net forecast decrease in 2021/22 capital expenditure of £29.7m (18.9% of the approved budget). The variations are detailed in Appendix 2.
2. To approve the updated four-year capital programme 2021-2025 of £473.4m as detailed in Appendix 1.
3. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 22-24.