Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Report will request authority to fund the
development for consultancy services up to the end of RIBA stage
3.
1. Appendix 1 is not for publication on the basis that it contains information relating to the financial or business affairs of any particular person (including the authority holding that information) as set out in paragraph 3 of Schedule 12A of the Local Government Act 1972 (as amended).
2. To consider, this Stage 1 (Feasibility) Development Appraisal Report and approve progression to Stage 2 (Planning) and Stage 3 (Procurement), for Hartopp Point and Lannoy Point site, Dawes Road, Fulham SW6.
3. To approve a project development budget of £3,715,262 for progression and delivery up to and including LBHF’s development stage 2 (i.e.: Planning or RIBA Stages 2 & 3) & stage 3 (i.e.: Procurement or RIBA Stage 4) to be funded from:
i. a previously approved budget of £250,000 for early feasibility work
ii. underspends of £198,062 and £500,000 from the previously approved CPO and acquisition budgets respectively for Hartopp Point and Lannoy Point
iii. a new budget of £2,767,200 from HRA borrowing.
4. To delegate authority to the Strategic Director for the Economy in consultation with the Cabinet Member for the Economy to extend appointments of the consultant teams beyond RIBA stage 1, in line with recommendation 1.2.
Report author: Omar Villalba
Publication date: 05/01/2021
Date of decision: 04/01/2021
Decided at meeting: 04/01/2021 - Cabinet
Effective from: 08/01/2021
Accompanying Documents: