Decision Maker: Cabinet Member for the Economy
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
This report recommends that a Pre-Construction
Services Agreement (PCSA) is entered into for the completion of the
technical design (RIBA Stage 4) for the refurbishment and fit-out
of the Town Hall. The budget has already been approved by Cabinet
and Full Council. This recommendation on the report is to confirm
appointment of the Contractor which will need drawdown on the
approved budget of £2.8m.
That the Council enters into a Pre-Construction Services Agreement (PCSA) with Ardmore Construction Limited to provide pre-construction services to the Council for the development of design of the Town Hall refurbishment and fit out as set out in `Contract A` the refurbishment of the existing Grade 2 Listed Building plus the fit out of the Town Hall (including Cat B fit out of the glass box vertical extension).
In December 2018, Cabinet approved the overall budget for the West Kings Street Renewal programme and agreed that a JV would be formed with A2Dominion. Following a contractor procurement exercise through the A2Dominion Contractor framework, the contractor, Ardmore, has been successful in the procurement. However, to enable stage one of a two-stage procurement process to commence formally, the JV is required to enter into a PCSA for Contract B and the Council is required to enter into a PCSA for Contract A.
For the avoidance of doubt, this approval is only for the commencement of pre- construction services between March and July 2020. A further approval will be requested to enter into the main construction contract once design and costs have been agreed in July 2020.
As described in the report.
Publication date: 18/05/2020
Date of decision: 17/05/2020
Effective from: 21/05/2020
Accompanying Documents: