Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Budget approval for the final phase of
Watermeadow Court Project including post completion site security
provision.
That Cabinet appr That Cabinet approves an additional budget of £526,000 for the Watermeadow Court development project to cover the unforeseen costs set out in paragraphs 11,12 and 13 of the report to be funded from capital receipts.
Report author: Kharon Williams
Publication date: 12/05/2020
Date of decision: 11/05/2020
Decided at meeting: 11/05/2020 - Cabinet
Effective from: 15/05/2020