Decision Maker: Leader of the Council
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To update members on the Ed City
Development
That the Leader
1. Approves an additional £6,176,142 to the General Fund capital budget funded by borrowing, giving a total capital budget of £65,202,000 for the construction of 132 residential units and associated professional fees and development management costs funded by the General Fund.
2. Approves a further £3,591,908 borrowing to fund the development in place of right to buy funding in order to release it to other parts of the development programme that haven’t secured GLA affordable housing grant as part of the Building Homes for Londoners grant programme.
The recommendations are required to allow the project to progress and for build contracts to be signed.
Option 1 – do not agree the budget
Option 2 – Revert to former specifications
Option 3 – approve the increase in budget
Publication date: 21/04/2020
Date of decision: 20/04/2020
Effective from: 24/04/2020
Accompanying Documents: