Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To provide proposals for the delivery and
funding of the 2015/2016 Corporate Planned Maintenance Programme
for the Council’s property portfolio.
1.1 That approval be given to 2015/2016 Corporate Planned Maintenance Programme and project budgets as set out in Appendix A to the report, subject to any amendments as agreed for operational reasons by the Executive Director of Finance and Corporate Governance and the Director for Building and Property Management.
1.2 That the 2015/2016 Corporate Planned Maintenance Programme will be monitored, incorporating operational changes made by the Executive Director of Finance and Corporate Governance and the Director for Building and Property Management, via progress reports to Corporate Asset Delivery Team and the appropriate Cabinet Member, be noted.
Report author: Mike Cosgrave
Publication date: 04/02/2015
Date of decision: 02/02/2015
Decided at meeting: 02/02/2015 - Cabinet
Effective from: 09/02/2015