Approval of the 2013/14 Highway Maintenance Programme

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The report seeks approval for the Carriageway and Footway 2013/14 Planned Maintenance Programme and authority to manage the programme and overall budget throughout the year.

Decision:

1.                  That the list of planned carriageway and footway maintenance schemes as set out in Appendix A of the report, be approved.

2.                  That authority be delegated to the Cabinet Member for Transport and Technical Services, in conjunction with the Executive Director of Transport and Technical Services and the Executive Director of Finance and Corporate Governance,  to make amendments to the programme as agreed for operational and cost effectiveness reasons in order to make the optimum use of resources allowing virements to contain expenditure within the approved resources and not subject to the normal virement rules.

3.                  That reports and updates on  programme amendments (additions and removals) to the approved scheme list be made to the Cabinet Member for Transport and Technical Services, be approved.

 

Report author: Jonathan Addis

Publication date: 12/02/2013

Date of decision: 11/02/2013

Decided at meeting: 11/02/2013 - Cabinet

Effective from: 18/02/2013

Accompanying Documents: