This report summarises the TfL funded integrated transport investment programme for 2012/13. Eighteen projects are proposed totalling £1.988 million under three programme areas; Corridors, Neighbourhoods and Smarter Travel.

The purpose of the schemes is to help meet the Transport Plan (LIP) objectives of improving access to the borough’s regeneration areas, improving the efficiency of the road network , improve the quality of our streets and air quality, make it easier for everyone to gain access to transport, control parking spaces fairly for residents and businesses and reduce the numbers of people killed and injured on our roads.

The funding has been provided specifically for these purposes by Transport for London and will be designed to give maximum value for money and reduce longer term maintenance costs to the Council . There will be full consultation on the details of schemes with residents, businesses and road user groups and schemes will only be supported if they have broad local support.

 

Decision:

 

  1. That approval be given to carry out feasibility design and consultation on projects C1 to C3 and N1 to N4 at a total cost of £217,000 (approximately 15% of the project total) as set out in paragraph 3 of the report.

 

  1. That authority be delegated to the Deputy Leader (Environment + Asset Management), in consultation with the Executive Director of Transportation and Technical Services, to approve implementation of the seven individual schemes (C1 to C3 and N1 to N4) subject to local consultation.

 

  1. That approval be given to complete the 2011/12 LIP projects, at a cost of £190,000 and to initiate the 2013/14 projects, at a cost of £50,000, as detailed in paragraph 4 of the report.

 

  1. That approval be given to deliver the smarter travel programme at a cost of £303,000, as detailed in paragraph 5 of the report.

 

  1. That approval be given to carry out stage 1 of the Shepherds Bush Town Centre West Major Project at a cost of £180,000, as detailed in paragraph 6 of the report.

 

Report author: Nick Boyle

Publication date: 07/03/2012

Date of decision: 05/03/2012

Decided at meeting: 05/03/2012 - Cabinet

Effective from: 12/03/2012

Accompanying Documents: