Decision details

Procurement Strategy for Nourish Hub Refurbishment Works

Decision Maker: Cabinet

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Procurement of contractor for refurbishment works

Decision:

1.    To approve the Nourish Hub Procurement Strategy and Business Case, as defined in Appendix 1, leading to the procurement of a works contractor to deliver refurbishment works and fit out for the Nourish Hub, using an open process.

 

2.    To delegate to the Strategic Director for the Economy, in consultation with the Cabinet Member for Economy, the decision to award and enter into contract with the preferred bidder, up to a value of £980,000.

 

Report author: Labab Lubab

Publication date: 02/07/2019

Date of decision: 01/07/2019

Decided at meeting: 01/07/2019 - Cabinet

Effective from: 05/07/2019

Accompanying Documents: