Decision Maker: Cabinet
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: Yes
This report seeks cabinet approval to
implement the Thames Path Improvement Scheme on Carnwath Road from
Broomhouse Dock, to Whiffin Wharf, and approval to spend the
estimated cost of the works.
Two separate agreements fund the cost of the works. Tideway through
a Sec106 and a sec278 agreement. This is in line with the
council’s commitment to being ruthlessly financially
efficient due to the cost being footed by a developer rather than
the council’s purse.
1. To approve the implementation and estimated cost of £416,000 of the improvement works on the Thames Path at Carnwath Road.
2. To place the order through the Council’s current highway term contract with FM Conway Ltd.
Report author: Michael Masella
Publication date: 04/06/2019
Date of decision: 03/06/2019
Decided at meeting: 03/06/2019 - Cabinet
Effective from: 10/06/2019