Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
The report requests additional funds be
allocated to the project to cover the cost of removing significant
fly-tipped material, and pay for site security.
1. That approval be given to allocate an additional £563,000 to the approved budget for the site clearance, enabling work and demolition of Watermeadow Court Housing Estate to cover the increased costs of site clearance and security under the demolition and enabling works contract funded by unrestricted capital receipts from the Decent Neighbourhoods programme and to note this will ultimately increase the Housing Capital Financing Requirement.
2. That approval be given to allocate an additional £95,000 to the already approved budget of £100,000 for increased Employer’s Agent consultancy fees, consultancy contingency and capitalised staff salaries and UK Power Networks utility disconnection costs funded by unrestricted capital receipts from the Decent Neighbourhoods programme and to note this will ultimately increase the Housing Capital Financing Requirement.
Report author: Matthew Doman
Publication date: 05/06/2018
Date of decision: 04/06/2018
Decided at meeting: 04/06/2018 - Cabinet
Effective from: 11/06/2018