Decision details

Nos.84 - 90b Fulham High Street - Section 106/Section 278 Highways Works

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

The Installation of a new footway buildout, with inset 'Loading' bays, 'Disabled Parking bays and associated highway works

Decision:

1.1.       To approve the implementation of the proposed Section 106 and Section 278 highway works at a cost of £133,000 for the works for Nos.84 – 90b Fulham High Street.

 

1.2.        To note that cost of the works will be funded by the developer Tesco Stores Limited.

 

Report author: Stephen Daway

Publication date: 17/01/2018

Date of decision: 15/01/2018

Decided at meeting: 15/01/2018 - Cabinet

Accompanying Documents: