Decision taken by the Cabinet Member on: 21 May 2014

 

1.1.        John Betts

 

1.1.1.   Subject to a formal agreement between the council and the school/ John Betts Foundation (St Peter's Hammersmith Schools Foundation) to ensure the continuance of the provision of a bulge class to allocate up to £444,000 (including VAT) for fit-out works to the ground floor of Ravenscourt house to be used for the provision of statutory education purposes.

 

1.2.        New King’s & Sulivan (re-location of Paray House from New Kings to Normand Croft)

 

1.2.1.   In line with the prior delegation given to waive standing orders, to appoint the Principal Contractor as Shaylor Group Ltd for the remodelling works of the Normand Croft School for the sum of £429,240.

 

1.3.        Wood Lane Special School

 

1.3.1.   To appoint 3BM as the Principal Contractor for the expansion of Wood Lane Special School for the sum of £750,000.

 

1.4.        Pope John

 

1.4.1.   To approve the allocation of a further £221,000 to fund the additional inflation cost of the contract resulting from delays incurred in resolving complex land title issues.

 

 

Publication date: 27/05/2014

Date of decision: 21/05/2014

Decided at meeting: 21/05/2014 - Cabinet Members' Decisions