Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Seeking approval for the 2014/15 planned capital street light column replacement programme, and maintenance work on highway assets.
1.1. That approval be given to use the budgets set out in Section 4.5 of the report to maintain and improve the Council’s lighting assets, using the existing public lighting term contractor.
1.2. That approval be given for capital replacement of columns that have reached the end of their serviceable life based on structural condition testing (an indicative programme for the replacement of older columns is attached in Appendices 1 and 2).
1.3. That authority to make amendments to the capital replacement programme as set out in Appendices 1 and 2 of the report for operational and cost effectiveness reasons, in order to make the optimum use of resources, be delegated to the Cabinet Member for Environment, Transport and Residents Services in conjunction with the Bi-borough Director of Transport and Highways.
Report author: Dean Wendelborn
Publication date: 12/08/2014
Date of decision: 11/08/2014
Decided at meeting: 11/08/2014 - Cabinet
Effective from: 18/08/2014
Accompanying Documents: