Issue - decisions

Contract Modification Report - Fit Out Works for 145 King St and 43 Beavor Lane

16/12/2019 - Contract Modification Report - Fit Out Works for 145 King St and 43 Beavor Lane

That the Strategic Director for the Economy, in consultation with the Cabinet Member for the Economy and the Arts, authorises the variation and inclusion of packages of works to the Call-Off Contract with Syntec Projects Ltd dated 24th June 2019 based upon the benchmarking exercises undertaken, and the additional expenditure required to settle the contract sum, as detailed in Appendix A of the report.